A project has four activities. Activity A has no predecessors and a duration of 1 week. Activity B has Activity A as its predecessor and a duration of 4 weeks. Activity C has Activity A as its predecessor and a duration of 3 weeks. Activity D has activities B and C as its predecessors and a duration of 2 weeks. What is the critical path for this project?
a. A ? B
b. A ? B ? D
c. A ? C ? D
d. Cannot be determined from the information given
b. A ? B ? D
You might also like to view...
A ______ is a standing plan that designates specific required action.
A. procedure B. industry standard C. rule D. policy E. certified procedure
The third step in the closing process is to transfer the balance in which of the following accounts to the permanent owner's equity account?
a. Revenue b. Expense c. Income Summary d. Owner's Capital
In the marketing mix, product refers to activities that communicate the merits of a product and persuade target customers to buy it
Indicate whether the statement is true or false
A person's attitude has three components: ________
A) affect, cognition, and behavior B) psychological, physiological, and situational C) situation, emotion, and environment D) cognitive, operant, and situational E) ritual, cultural, and referential