A project manager learns that her project has an EV of 1200, AC of 1100 and PV of 1000. What can the project manager report regarding this project?
Fill in the blank(s) with the appropriate word(s).
Answer will vary
The project has a position CV of $100. This indicates that $100 less was spent on actual work performed than what was planned. The project has a positive SV of $200. This indicates that $200 worth of work has been completed that wasn't planned at this time. In order to be sure that this work includes critical activities, the project manager must look at the tracking Gantt chart. Efficiency indexes can also be reported and interpreted. CPI = 1.09 and the SPI is 1.2.
You might also like to view...
The units-of-output depreciation method provides a good match of expenses against revenue
a. True b. False Indicate whether the statement is true or false
The two major product categories are business and institutional.
Answer the following statement true (T) or false (F)
Explain the legal ramifications of attempts to control distribution functions.
What will be an ideal response?
A firm is evaluating an investment proposal which has an initial investment of $5,000 and cash flows presently valued at $4,000. The net present value of the investment is:
A) -$1,000 B) $0 C) $1,000 D) $1.25