The variance of a project’s completion time is determined by the?

a. Sum of all project activity variances
b. Sum of all project activity durations
c. Sum of all critical path activity variances
d. Sum of all critical path activity durations


c. Sum of all critical path activity variances

Business

You might also like to view...

If one country is hit with a shock that increases its income and its demands for imported goods and services from other countries, thus increasing aggregate demand in those countries, then the business cycle is being transmitted internationally through ____ effect.

A. a trade B. an interest-rate C. an exchange-rate D. an expected-inflation

Business

Unstructured problems and the use of models are characteristics that describe a decision support system

Indicate whether the statement is true or false

Business

What element below is defined as moderate level of stressors that have constructive and positive effects on effort and performance?

A. strain B. distress C. stress D. eustress

Business

Balser Corporation manufactures and sells a number of products, including a product called JYMP. Results for last year for the manufacture and sale of JYMPs are as follows:   Sales   $960,000  Less expenses:      Variable production costs$464,000    Sales commissions 144,000    Salary of product manager 100,000    Fixed product advertising 160,000    Fixed manufacturing overhead 132,000  1,000,000  Net operating loss   $  (40,000)?Balser is trying to decide whether to discontinue the manufacture and sale of JYMPs. All expenses other than fixed manufacturing overhead are avoidable if the product is dropped. None of the fixed manufacturing overhead is avoidable.Assume that dropping Product JYMP will have no effect on other products. The annual

financial advantage (disadvantage) for the company of eliminating this product should be: A. ($132,000) B. ($172,000) C. $40,000 D. ($92,000)

Business