The variance of a project’s completion time is determined by the?
a. Sum of all project activity variances
b. Sum of all project activity durations
c. Sum of all critical path activity variances
d. Sum of all critical path activity durations
c. Sum of all critical path activity variances
You might also like to view...
If one country is hit with a shock that increases its income and its demands for imported goods and services from other countries, thus increasing aggregate demand in those countries, then the business cycle is being transmitted internationally through ____ effect.
A. a trade B. an interest-rate C. an exchange-rate D. an expected-inflation
Unstructured problems and the use of models are characteristics that describe a decision support system
Indicate whether the statement is true or false
What element below is defined as moderate level of stressors that have constructive and positive effects on effort and performance?
A. strain B. distress C. stress D. eustress
Balser Corporation manufactures and sells a number of products, including a product called JYMP. Results for last year for the manufacture and sale of JYMPs are as follows: Sales $960,000 Less expenses: Variable production costs$464,000 Sales commissions 144,000 Salary of product manager 100,000 Fixed product advertising 160,000 Fixed manufacturing overhead 132,000 1,000,000 Net operating loss $ (40,000)?Balser is trying to decide whether to discontinue the manufacture and sale of JYMPs. All expenses other than fixed manufacturing overhead are avoidable if the product is dropped. None of the fixed manufacturing overhead is avoidable.Assume that dropping Product JYMP will have no effect on other products. The annual
financial advantage (disadvantage) for the company of eliminating this product should be: A. ($132,000) B. ($172,000) C. $40,000 D. ($92,000)