An activity must be crashed on each critical path in order to reduce project duration.

Answer the following statement true (T) or false (F)


True

In order to reduce project duration each critical path must be crashed.

Business

You might also like to view...

Which of the following statements about current liabilities is true?

a. Current liabilities are listed in order of decreasing amounts in the current liability section of the balance sheet. b. The amount of current liabilities has little implication for a company's liquidity. c. The current liability section never contains any portion of long-term liabilities. d. The current ratio is defined as current assets divided by current liabilities.

Business

On weekends, Everett often finds himself thinking about his customers and their problems. Sometimes Everett will figure out a potential solution and e-mail or call his customer. What personal trait does Everett have that is important to sales success?

What will be an ideal response?

Business

Bridget Company manufactures candles

The standard direct materials quantity required to produce one large candle is 1 pound at a cost of $5 per pound. Every candle requires 2 direct labor hours at a standard cost of $3 per direct labor hour. During November, 7,200 large candles were produced using 7,500 pounds costing $45,000. At the end of November, an examination of the labor cost records showed that the company used 15,000 direct labor hours (DLHr) at a cost of $4 per hour. Using the format below, prepare an analysis of the direct labor cost variances. What will be an ideal response

Business

Explain the concept of marketable title

Business