Critical Thinking Questions
Mauricio, a project manager at a reputed firm, has been assigned to handle a new project that the firm has received. This project involves a lot of scheduling that has to be handled by Mauricio.
Mauricio estimates that the first module of the project could be completed in as few as 15 days or could take as many as 25 days, but most likely will require 20 days. What is the 20 day estimate called?
A. best-case estimate (B)
B. probable-case estimate (P)
C. worst-case estimate (W)
D. logistical estimate (L)
Answer: B
Computer Science & Information Technology
You might also like to view...
How can you make a clip offline?
What will be an ideal response?
Computer Science & Information Technology
___________ is an advantage of JAD.
A. Can produce excellent documentation B. Helps clarify user requirements C. Improves the process of rewriting legacy applications D. New system has lower training
Computer Science & Information Technology
Two types of cameras used today are point-and-shoot cameras and state-of-the-art _______________ cameras, which allow you to change the lens.
Fill in the blank(s) with the appropriate word(s).
Computer Science & Information Technology
A card is drawn from a standard deck of playing cards. What is the probability that the card is not a/an 5?
A.
B.
C.
D.
E.
Computer Science & Information Technology