Given the following information for a project, what are the estimated slack times (in weeks) for activities A-H?
Activity Immediate Processor Activity Time (days)
A - 6
B - 8
C A, B 5
D B 4
E C 7
F C, D 3
G D 6
H E, F, G 5
CP = Critical Path
Answer: (A=2; B=0; C=0; D=2; E=0; F=4; G=2; H=0)
Activity ES EF LS LF Slack CP
A 0 6 2 8 2 No
B 0 8 0 8 0 Yes
C 8 13 8 13 0 Yes
D 8 12 10 14 2 No
E 13 20 13 20 0 Yes
F 13 16 17 20 4 No
G 12 18 14 20 2 No
H 20 25 20 25 0 Yes
You might also like to view...
Elaborate on the role of a public relations specialist
What will be an ideal response?
Suggett Corporation's net cash provided by operating activities was $34; its income taxes were $12; its capital expenditures were $24; and its cash dividends were $7. The company's free cash flow was:
A. $15 B. $(19) C. $77 D. $3
What is the second step in developing a practical social media plan?
A. Identify target audience B. Define your value C. Make personal connections D. Identify success metrics E. Define your goals
If the bond's coupon was smaller than 10%, the modified duration would be _____ compared to the original modified duration.
Steel Pier Company has issued bonds that pay semiannually with the following characteristics:
A. larger
B. unchanged
C. smaller
D. The answer cannot be determined from the information given.