Classify the following problems as to whether they are pure-integer, mixed-integer, zero-one, goal, or nonlinear programming problems
(a) Maximize Z = 5 X1 + 6 X1 X2 + 2 X2
Subject to: 3 X1 + 2 X2 ? 6
X1 + X2 ? 8
X1, X2 ? 0
(b) Minimize Z = 8 X1 + 6 X2
Subject to: 4 X1 + 5 X2 ? 10
X1 + X2 ? 3
X1, X2 ? 0
X1, X2 = 0 or 1
(c) Maximize Z = 10 X1 + 5 X2
Subject to: 8 X1 + 10 X2 = 10
4 X1 + 6 X2 ? 5
X1, X2 integer
(d) Minimize Z = 8 X12 + 4 X1 X2 + 12 X22
Subject to: 6 X1 + X2 ? 50
X1 + X2 ? 40
(a) nonlinear
(b) zero-one
(c) pure integer
(d) nonlinear
You might also like to view...
Integrated Computers, Inc. wants to compile a profile of the customer it will target in its next promotional mailing. What environment would this be found in?
A. Internal B. Task C. Work D. General E. None of these
A limited liability company (LLC) can elect to be taxed as a corporation.
Answer the following statement true (T) or false (F)
$1,200 is received at the beginning of year 1, $2,200 is received at the beginning of year 2, and $3,300 is received at the beginning of year 3
If these cash flows are deposited at 12 percent, their combined future value at the end of year 3 is ________. A) $ 6,700 B) $17,072 C) $12,510 D) $ 8,142
When using the "buy term and invest the rest" strategy, the easiest way to ensure your money is actually invested is to set up
a. an automatic investment program (AIP) with a mutual fund. b. cash-value life insurance. c. cash-value life insurance. d. a settlement option plan.