Which of the following is NOT a good reason to terminate (kill) a project?
A. Consistent budget and schedule overruns.
B. Changing organizational priorities.
C. Uncertainty regarding the project’s outcomes.
D. Wrong resources assigned to the project.
C. Uncertainty regarding the project’s outcomes.
Explanation:
All projects have some degree of uncertainty.
You might also like to view...
The straight-line depreciation method is a conservative depreciation method
Indicate whether the statement is true or false
A divorce is the only method for legally terminating a marriage
Indicate whether the statement is true or false
A merchandiser returned inventory worth $2,000 that was purchased on account. Under the periodic inventory system, the journal entry to record the return would include ________
A) a debit to Purchase Returns and Allowances for $2,000 and a credit to Accounts Payable for $2,000 B) a debit to Accounts Payable for $2,000 and a $2,000 credit to Purchase Returns and Allowances C) a debit to Purchases for $2,000 and a credit to Accounts Payable for $2,000 D) a debit to Accounts Payable for $2,000 and a credit to Purchases for $2,000
Eurobonds are typically issued as registered bonds rather than bearer bonds.?
Answer the following statement true (T) or false (F)