An activity has an optimistic time estimate of 17 days, a most likely estimate of 22 days, and a pessimistic estimate of 32 days. What is the expected duration of the activity?
A) 22.83 days
B) 23.67 days
C) 24.33 days
D) 25.17 days
A
You might also like to view...
The 10-K report filed annually with the SEC is basically aimed toward which of the following groups?
a. Shareholders b. Professional financial analysts c. Management d. All of the above
Individual-oriented cultures include China and Latin America
Indicate whether the statement is true or false.
______ is considered a continuous process of systematic advancement, of “becoming increasingly more complex, more elaborate and differentiated, by virtue of learning and maturation.”
a. Education b. Training c. Development d. Learning
Managers who are responsible for developing an organization’s mission statement are:
a. middle managers b. first-line managers c. department managers d. executive managers e. democratic managers