The figure above shows a timeline that includes milestones, the date the project will be completed, and who is responsible for each task. Normally, you do NOT need to include ____ in the timeline.
A. milestones
B. completion date
C. person responsible for each task
D. None of the above, all of these items should be included
Answer: D