When completing a forward pass, you carry the early finish to the next activity where it becomes its early start unless the next succeeding activity is a merge activity. In this case you select the smallest early finish number of all its immediate predecessor activities.
Answer the following statement true (T) or false (F)
False
When completing a forward pass, you carry the early finish to the next activity where it becomes its early start unless the next succeeding activity is a merge activity. In this case you select the largest early finish number of all its immediate predecessor activities. This makes sense because all preceding activities must be complete before an activity can start.
You might also like to view...
When giving a(n)______, you simply deliver a persuasive argument on a controversial issue.
a. debate b. position presentation c. poster presentation d. argument presentation
Weekly usage of a product is 8 units. Since the plant operates 50 weeks per year, this leads to annual usage of 400 units. Setup cost is $40 and annualized carrying cost is $80. Weekly production of this product is 12 units
Lead time is four weeks, and safety stock is one week's production. What is optimal kanban size? What is the optimal number of kanbans?
Which of the following is a drawback of the SWOT analysis?
A. The SWOT analysis takes into account only the internal environment of a firm, ignoring the equally important external environment. B. A problem with this framework is that a strength can also be a weakness, and that an opportunity can also simultaneously be a threat. C. This framework is only applicable to the manufacturing industries; it is ineffective when applied to the service firms. D. A drawback of this framework is that it allows managers to evaluate only a firm's current situation and not its future prospects.
Indexes are created in most RDBMSs to:
A) provide a quicker way to store data. B) decrease the amount of disk space utilized. C) provide rapid random and sequential access to base-table data. D) increase the cost of implementation.