During the MMPT P&O process, how does a charge controller determine when the MMP has been reached?

What will be an ideal response?


The MPPT starts by setting a load value and measuring the module output voltage V1 and the current. The power (P1) at V1 is calculated. Next, the load is increased and power is calculated at several points until it is less than the power calculated at the previous point, indicating that the MMP has been passed. At this point, the MPPT reverses back to the previous voltage and then goes back and forth (oscillates) between the two voltages on either side of the MPP.

Trades & Technology

You might also like to view...

?The classification of flux depends on ____.

A. ?its chemical composition B. ?the mechanical properties of the weld metal deposited C. ?the range of manganese D. ?the carbon points

Trades & Technology

In an alternator the generated AC current is changed to DC current by the use of ________

A) Conductor windings B) Polarity springs C) Diodes D) Slip rings

Trades & Technology

When designing stairs for residential construction, safety and ease of use are the most important factors

Indicate whether the statement is true or false

Trades & Technology

What is ASCII?

What will be an ideal response?

Trades & Technology