Which of the following refers to the time in which an activity can be completed without delaying the project?
A) Latest expected completion time
B) Earliest expected completion time
C) Delay time
D) End time
E) Critical time
A
Explanation: A) The latest expected completion time tells us what the very latest time is for an activity to be completed before the project is delayed. This applies to activities along the critical path.
You might also like to view...
A ________ is a chart that displays data in bars positioned horizontally or vertically
A) line chart B) pictograph C) bar chart D) pie chart E) grid
Nerdo Computers had an insurance policy on its premises, for which it paid a premium of $525 per year. It found a new broker who offered a much lower rate, so it wrote to its current broker to cancel its existing policy
The broker replied that there would be a $100 cancellation fee. Which of the following facts or arguments would help Nerdo avoid having to pay the fee? A) If the fee is not mentioned in the contract B) If the fee can be characterized as a penalty C) If the fee is not a genuine pre-estimate of damages. D) Both B and C E) All of the above
Distinguish between the concepts of the maturity-risk premium and the liquidity-risk premium
What will be an ideal response?
Two thousand numbers are selected randomly; 960 are even numbers
a. State the hypotheses to determine whether the proportion of odd numbers is significantly different from 50%. b. Compute the test statistic. c. At the .10 level of significance using the p-value approach, test the hypotheses.