What occurs when two tasks in a ControlLogix project are assigned the same priority number?

What will be an ideal response?


If any two tasks are assigned the same priority number, they simply alternate, a situation known as time slicing.

Computer Science & Information Technology

You might also like to view...

Match each item with a statement below.

A. can span more than one hard drive B. used to enhance the amount of RAM in a system C. rearranges files on the drive into as few segments as possible D. an extra copy of a data or software file that you can use if the original file becomes damaged or destroyed E. a volume that can be accessed by way of a folder on another volume so that the folder has more available space F. searches for bad sectors on a volume and recovers the data from them if possible G. a hidden file stored in the root directory of drive C H. can be partitioned and formatted as a stand-alone hard drive I. snapshots of the system and include Windows system files that have changed J. the overall structure an OS uses to name, store, and organize files on a drive

Computer Science & Information Technology

Explain the difference between a bound control and an unbound control

What will be an ideal response?

Computer Science & Information Technology

If a scheduled Start date is after the Status date, that task is set to ____ complete.

A. 0% B. 5% C. 25% D. 100%

Computer Science & Information Technology

When using File Explorer, double chevrons (<<) indicate that the current path is too long to fit in the address bar

Indicate whether the statement is true or false

Computer Science & Information Technology