Which of the following is a major drawback of the bottom-up approach to Six Sigma projects?
a. The projects are too broad in scope to be completed in a timely manner.
b. The projects are not well suited to the capabilities of the teams as they are chosen by top management who may not be aware of the capabilities of the teams.
c. The projects receive little support and low recognition from the top management.
d. The top managers underestimate the cost and overestimate the capabilities of the team or teams to which the project is assigned.
c
You might also like to view...
A digital signature is a digital copy of the sender's actual signature that cannot be forged
Indicate whether the statement is true or false
United Insurance Agency incurred the following activity costs related to service quality. Total sales $1,000,000 Costs of quality: Prevention 50,000 Appraisal 47,000 Internal failure 36,000 External failure 64,000 Costs of conformance total
a. $15,500. b. $55,000. c. $120,000. d. $131,400.
In a resource-constrained project the third priority in assigning resources is usually given to activities with the
A. Lowest identification number. B. Smallest duration. C. Least slack. D. Most slack. E. Highest cost.