Activities G, P, and R are the immediate predecessors for activity W. If the earliest finish times for the three are 12, 15, and 10, then the earliest start time for W
a. is 10.
b. is 12.
c. is 15.
d. cannot be determined.
C
You might also like to view...
When a receiver can no longer determine what information is useful and what is useless, or think deeply about complex situations, they are suffering from information overload
Indicate whether the statement is true or false.
A limited partnership must have at least one general partner
Indicate whether the statement is true or false
October November December Budgeted S&A Expenses Salary expenses10,000 10,500 11,000 Sales commissions, 5% of sales5,000 5,500 5,300 Insurance expenses2,000 2,000 2,000 Rent2,400 2,400 2,400 Depreciation on equipment1,500 1,500 1,500 Utilities1,100 1,300 1,500 Total operating expenses22,000 23,200 23,700 Schedule of Cash Payments for S&A Expenses Salary Expenses? 10,500 ? 100% of prior month sales commissions5,100 ? ? Insurance Expense2,000 2,000 2,000 Rent? ? 2,400 100% of Prior months utilities expenses1,200 ? ? Total payments foe S&A expenses? ? ? What is the total amount of S&A expenses for the fourth quarter that the company will report on its pro forma income statement?
A. $64,400 B. $23,700 C. $63,900 D. $68,900
What is the Goldilocks Rule, and give an example of how it applies to goal-setting theory?
What will be an ideal response?