An activity performed by a subcontractor is scheduled for 20 weeks at an anticipated cost of $100,000. Due to slippage on the critical path you need to reduce this activity by three weeks

If the subcontractor informs you that the activity can be completed in 16 weeks for $200,000, what is the slope for the activity?
A) $5,000 per week
B) $33,333 per week
C) $25,000 per week
D) $12,500 per week


C

Business

You might also like to view...

For both debt accounts and stockholders' equity accounts, the boxes of evidence would typically be filled only with evidence obtained through substantive procedures

a. True b. False Indicate whether the statement is true or false

Business

When looking at the stakeholder characteristics of power, legitimacy, and urgency, ______.

a. power should be given the most attention b. the presence of any one characteristic should be carefully considered by managers c. urgency should be given the most priority d. manager should not fail to neglect personal affiliation or emotional connection

Business

In business presentations, when presenting as a team, ________

A) everyone on the team must participate equally in the presentation B) avoid introducing the next presenter C) interrupt immediately if a teammate forgets to mention a point D) practice transitions from person to person E) be prepared to present your own slides only

Business

______ is a situation where the organization takes an adverse employment action against an employee because the employee brought discrimination charges against the organization or supported someone who brought discrimination charges against the company.

A. Discrimination B. Turnover C. Participation D. Transparency E. Retaliation

Business