The damages that are typically recoverable when a contract has been breached and one party has suffered loss are called:
A) punitive damages
B) emotional distress damages.
C) compensatory damages.
D) liquidated damages.
C
You might also like to view...
Training of team members should include:
A) Action skills B) Mathematic skills C) Public speaking skills D) Reading skills
The universal functions of marketing can be performed by
A. intermediaries. B. consumers. C. producers. D. collaborators. E. all of these.
Heidi was part of a project team that retained their roles within the organization and was on loan to the project due to her technical expertise. In effect, she reported to two bosses, one in her functional area and also to the project manager
Heidi is operating within a(n) ________ organizational structure. Fill in the blanks with correct word
In Scheerer v. Fisher where Scheerer, a real estate agent, sued Fisher for failing to pay Scheerer for his services in locating property for Fisher, the appeals court held that:
a. there was no contract or basis for payment to Scheerer b. there was an implied contract and so Scheerer must be paid c. there was implied contract, but there was no need to pay Scheerer since the original deal fell through d. there was no contract, but Scheerer should be paid anyway, out of good will e. none of the other choices are correct