For solar hot water, there should be an area ____ adjacent to the conventional water heater in the utility room for the future solar hot water tank.

A. 3' x 2' x 6'
B. 3' x 3' x 8'
C. 4' x 2' x 7'
D. 4' x 3' x 8'


Answer: C

Trades & Technology

You might also like to view...

Technician A says that the starter control circuit includes the ignition switch, neutral safety (clutch) switch, and solenoid. Technician B says that the power circuit includes the battery, battery cables, solenoid, and starter motor. Which technician is correct?

A) Technician A only B) Technician B only C) Both technicians D) Neither technician

Trades & Technology

CAD technicians who perform quantity takeoffs are called upon to determine the ____ of steel reinforcing bars needed for the project.

A. linear feet B. cubic tons C. total number D. tensile strength

Trades & Technology

Answer the following statement(s) true (T) or false (F)

1. An engineering drawing is an important document in an organization because it affects the success of both the product and the organization. 2. The function of a product determines the amount of variation permitted for each dimension. 3. Engineering drawings cannot be used as evidence in product litigation cases. 4. The ISO standards are created in the U.S., but are used globally. 5. Dimensioning and tolerancing standards are used on most engineering drawings around the world.

Trades & Technology

The theoretically exact location of the center of a hole is known as:

a. position b. exact position c. true position d. theoretical position

Trades & Technology