Answer the following statements true (T) or false (F)
1. The work breakdown structure identifies the individual work packages necessary to accomplish the project.
2. The time-phased budget enables the project team to determine when budgeted money is likely to be spent on completion of tasks.
3. The project’s baseline is the standard against which we compare project performance, project cost, and project schedule.
4. Unlike the standard S-curve evaluation, the EVM variance is meaningful because it is based not simply on the budget spent but on value earned.
5. The work breakdown structure identifies the human and material resources assigned to the project.
1. True
2. True
3. True
4. True
5. True
You might also like to view...
Which of the following characteristics of a great company distinguishes it from an ordinary company?
A) It keeps its purpose and mission limited. B) It views itself only as a money-making machine. C) It sees itself as a key social institution. D) It always adapts a product-centric marketing approach.
When a process is in control, only ________ variations exist in the process
Fill in the blanks with correct word
Home Depot shareholders rebelled because:
a. Of excessive compensation and poor earnings performance. b. The failure of board members to face shareholders. c. They were not given discounts at stores. d. Both a and b e. All of the above
A discharge does not release a person from a consumer debt to a single creditor totaling more than $5,775 for luxury goods or services if the debt was incurred within how many days of the order for relief?
A) 90 B) 120 C) 180 D) 365