The network below represents a project being analyzed by the critical path method. Activity durations are indicated on the network

a. Identify the activities on the critical path.
b. What is the duration of the critical path?
c. Calculate the amount of slack time at activity H.
d. If activity I were delayed by ten time units, what would be the impact on the project duration?


(a) Critical activities are A-C-J-K; (b) The critical path is 26 time units; (c) Slack at H is 9 units; (d) I has 11 units slackā€”a ten unit delay would have no impact on the project.

Task Early Start Early Finish Late Start Late Finish Slack
A 0 5 0 5 0
B 0 3 6 9 6
C 5 16 5 16 0
D 0 4 9 13 9
E 3 10 9 16 6
F 4 10 15 21 11
G 3 7 17 21 14
H 4 7 13 16 9
I 10 15 21 26 11
J 16 22 16 22 0
K 22 26 22 26 0
Project 26

Business

You might also like to view...

Describe time inconsistency and explain how it can be avoided by a central bank setting monetary policy.

What will be an ideal response?

Business

Which of the following gives the reader some context and may point to a conclusion offered in the section?

A) Heading B) Subheading C) Major heading D) Descriptive heading E) Informative heading

Business

An example of an economic regulatory agency is:

A. National Highway Traffic Safety Administration. B. National Labor Relations Board. C. Consumer Product Safety Commission. D. Equal Employment Opportunity Commission.

Business

You may only specify one person as a primary beneficiary

Indicate whether the statement is true or false

Business