Identify the order of the steps for the general lockout/tagout procedure:
____ Isolate and de-energize all sources of energy to the equipment.
____ Confirm isolation with maintenance and add maintenance tags.
____ Stop the equipment.
____ Tag the start/stop station.
____ Isolate the equipment (in other words, block, tag, and lock all process lines).
____ Centralize the isolation keys in an area with restricted access (for example, a lockout/tagout lockbox).
1. Stop the equipment.
2. Isolate the equipment (in other words, block, tag, and lock all process lines).
3. Isolate and de-energize all sources of energy to the equipment.
4. Tag the start/stop station.
5. Centralize the isolation keys in an area with restricted access (for example, a
lockout/tagout lockbox).
6. Confirm isolation with maintenance and add maintenance tags
You might also like to view...
What should the technician use when checking for diagnostic trouble codes?
A) Any enhanced scan tool that can read body and/or chassis codes B) Only a factory scan tool can be used C) Any global (generic) scan tool that can read body and/or chassis codes D) A paper clip, because it is needed to read codes
The role of microtubules in a eukaryotic cell is to:
a. Break down molecules and waste materials b. Prepare proteins for export from the cell c. Help move chromosomes during division d. Serve as cell storage compartments
A symbol in which a circle is below the reference line and tangent to it has the number 200 mm shown to the right of the circle. Directly below the circle is the number 6 in parentheses. The letters "SMAW" are shown in the tail. What does this symbol signify?
A. Spot welds 200 mm in diameter are to be placed on the arrow side of the object. There are to be 6 welds, each placed with the shielded metal arc welding process. B. 6 spot welds are to be placed on the arrow side of the object 200 mm apart with the welds placed with the shielded metal arc welding process. C. Seam welds are to be placed on the arrow side of the object, 200 mm apart with the welds penetrating a distance of 6 mm. D. A weld all around with a thickness of 200 mm is to be placed with a penetration of 6 mm. E. None of the above. This is an incorrect symbol.
The best method of cleaning new brick masonry is _____.