In wood frame construction, preparation for hanging cabinets involves the installation of _____.
a. backing boards
b. support rails
c. metal hangers
d. T-braces
Answer: A
You might also like to view...
Actual measurements for construction are taken from the _____.
a. primary control points b. secondary control points c. subsidiary control points d. working control points
Special wells are often drilled in the center of the irrigation area to save costs
Indicate whether the statement is true or false.
Which of the following is a correct statement about uses of PERT and Gantt:
a. PERT and Gantt are used primarily for project planning and scheduling. b. PERT and Gantt are useful for planning only when you have historical data on sales. c. PERT and Gantt are useful for environmental scanning and competitor intelligence. d. PERT and Gantt are qualitative techniques for planning. e. None of the above is true for PERT and Gantt.
Drawing the bond pattern lets the mason calculate _____.