Given the earliest and latest finish times for each of these activities, what are the activity lengths?
Activity EF LF Predecessors
A 3 3 --
B 10 10 A
C 5 13 A
D 18 18 B
E 15 18 B
F 11 19 C
G 8 19 C
H 23 23 D, E
I 15 23 F, G
J 24 24 H, I
What will be an ideal response?
Answer:
Activity Duration
A 3
B 7
C 2
D 8
E 5
F 6
G 3
H 5
I 4
J 1