Use the information in the table to sketch the network and compute early and late start times
Activity Time Predecessor
A 8
B 4 A
C 5 B, F
D 12 A
E 8 D
F 4 D
G 9 E, F
H 12 G
I 6 C, G
J 5 I
K 9 H
L 12 J, K
The early and late start times are shown in the table and the network is below:
Task Early Start Early Finish Late Start Late Finish
A 0 8 0 8
B 8 12 38 42
C 24 29 42 47
D 8 20 8 20
E 20 28 20 28
F 20 24 24 28
G 28 37 28 37
H 37 49 37 49
I 37 43 47 53
J 43 48 53 58
K 49 58 49 58
L 58 70 58 70
You might also like to view...
An employee has a(n) ______________________________ when he (she) has a financial interest (direct or indirect) in a company with which the employer does business
Fill in the blank(s) with correct word
Subway restaurants are positioned as offering healthy, good-tasting sandwiches. When the competitive frame of reference is quick-serve restaurants like McDonald's, what is the POD?
A) health B) taste C) convenience D) price E) brand
All property, plant, and equipment assets are depreciated over time
Indicate whether the statement is true or false
While preparing a contribution margin income statement, the costs are shown into which of the two categories?
A) Direct materials and indirect materials B) Product and period C) Variable and fixed D) Avoidable and unavoidable