When activity times are uncertain,

a. assume they are normally distributed.
b. calculate the expected time, using (a + 4m + b)/6.
c. use the most likely time.
d. calculate the expected time, using (a + m + b)/3.


B

Business

You might also like to view...

Cascading headings help your readers to navigate the material in your report

Indicate whether this statement is true or false.

Business

If customer requirements vary, the firm would need ______.

a. a few large consolidated facilities b. several smaller localized facilities c. a few smaller localized facilities d. several large consolidated facilities

Business

Jacob sends an e-mail to his team describing the implementation of a new work practice. However, in the e-mail he does not solicit comments or suggestions from his subordinates. He feels that the subordinates lack the experience required to effectively evaluate the various implications of the new practice. This is an example of

A. one-way communication. B. nonverbal communication. C. participative decision making. D. participative problem solving. E. interactive communication.

Business

Tyler runs a parasailing business on Hilton Head Island, South Carolina. Tyler closes his business in winter when the water gets too cold. Tyler should use a ________ advertising schedule.

A. continuous B. purposeful C. penetrating D. pulsing E. flighting

Business