The time required to complete a project is known to be normally distributed with a mean of 44 weeks and a standard deviation of 8 weeks
(a) What is the probability that the project is finished in 40 weeks or fewer?
(b) What is the probability that the project is finished in 52 weeks or fewer?
(c) There is a 95 percent chance that the project will be finished in fewer than how many weeks?
(a) 0.30854 (b) 0.84135 (c) 44 + 1.645(8 ) = 57.16
You might also like to view...
Which of the following is NOT an acceptable task for a retail store manager?
A) making the cash deposit at the bank B) proving the cash by comparing the cash in the drawer against the point-of-sale terminal's record of cash sales C) using the point-of-sale terminal's tape to record the journal entry for sales revenue D) overseeing the work of the sales clerks
Compare and contrast the purpose and content of a branded community Web site to that of a marketing Web site
What will be an ideal response?
______ is the process of creating a reasonable pool of qualified candidates for a job opening.
A. Retraining B. Rehiring C. Yield Ratio D. Recruiting
Angie was threatened by her supervisor with a negative outcome for failure to submit to a sexual relationship. This is referred to as:
A. disparate treatment B. disparate impact C. hostile work environment D. undue hardship E. quid pro quo harassment