The critical path for the network activities shown below is ________ with duration ________

Activity Duration Immediate
Predecessors
A 2 --
B 4 --
C 6 A,B
D 1 A,B
E 2 B,C,D

A) A-D-E; 5
B) B-E; 6
C) B-D-E; 7
D) A-C-E; 10
E) B-C-E; 12


E

Business

You might also like to view...

Financial intermediaries spread their risk by providing funds to a large number and variety of borrowers by offering many different types of loans. Due to this, the loan portfolios of intermediaries are said to be _____.

A. well diversified B. well consolidated C. economically efficient D. partially underwritten E. partially shelf registered

Business

Budgeting for promotion expenditures by computing a percentage of past or expected sales

A. will increase promotional expenditures when business is poor. B. is the most common method of setting the promotion budget. C. is a complex method of budgeting. D. is especially suitable for new products. E. None of these answers is correct.

Business

People can create natural resources by growing and harvesting agricultural products.

Answer the following statement true (T) or false (F)

Business

Containers organize and present visual controls for a ________ purpose

A) specific B) general purpose C) future D) visual

Business