A project's duration can be reduced by:
A) Shortening the duration of critical path tasks.
B) Adding tasks to the critical path.
C) Adding shorter routes around the critical path.
D) Completing the backward pass first.
A
You might also like to view...
In order to construct a confidence interval estimate of the population mean, the value of
must be given.
Answer the following statement true (T) or false (F)
What is distribution intensity? What are the levels of distribution intensity?
What will be an ideal response?
The Homer Corporation produces two products, and reports the following production and cost information for the most recent accounting period. Product A Product BNumber of units produced 10,000units 2,000unitsDirect labor @ $20 per direct labor hour (DLH) 0.50DLH per unit 2.00DLH per unitDirect materials cost$2per unit $30per unit Overhead costs:Total Cost ActivityDriverProduct AProduct BMachine setup$1,200.00 setups5setups15setupsQuality inspections 24,000.00 inspections60inspections140inspectionsTotal$25,200.00 Using activity-based costing to assign overhead costs, the total product cost per unit for Product B is:
A. $13.40 per unit B. $78.85 per unit C. $75.60 per unit D. $12.75 per unit E. $14.60 per unit
Leasing Equipment Corporation (LEC) agrees to lease five computer workstations to Mapmakers, Inc. Before any interest in the workstations can pass from LEC to Mapmakers, they must be
A. in existence and identified as the goods in the contract. B. in LEC's physical possession. C. in Mapmakers's physical possession. D. listed in a document of title and filed in the appropriate state office.