Checking for available capacity at the materials requirements planning level is done in which process?

a. master scheduling
b. capacity requirements planning
c. resource planning
d. rough-cut capacity planning


b. capacity requirements planning

Business

You might also like to view...

A thank-you message should be sent ________ an interview

A) two days after B) at least thirty hours after C) within twenty four hours of D) one week after E) on the third day from the date of

Business

Duski, a very expensive brand of clothing and accessories, promotes its products by using advertisements that feature beautiful women wearing its products. What kind of an advertising appeal is used by Duski?

a. Environmental consciousness b. Vanity and egotism c. Health d. Profit

Business

The cost object in a process costing system is the specific job.

Answer the following statement true (T) or false (F)

Business

Which of the following U.S. antimonopoly laws deals with "tying contracts," where the sale of one product is contingent on the business customer purchasing other products from the same supplier?

A. Sherman Act (1890) B. Wheeler-Lea Amendment (1938) C. Clayton Act (1914) D. Robinson-Patman Act (1936) E. Antimerger Act (1950)

Business