Which of the following is the critical path?
A. Path 1 takes 18 days.
B. Path 2 takes 14 days.
C. Path 3 takes 22 days.
D. Path 4 takes 16 day.
C. Path 3 takes 22 days.
You might also like to view...
Devon Manufacturing Company purchased a new canning machine on July 1, 2015, for $190,000. The estimated salvage value is $15,000. The company uses units-of-production depreciation and estimates the machine will produce 125,000 units during its useful life. In 2015, the company manufactured 5,000 units after acquiring the machine. Depreciation expense for 2015 will be
A) $7,600 B) $6,500 C) $7,000 D) $14,000
Use this earned schedule table to determine the schedule variance ($) for this project at the end of Month 6
Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 PV ($) $125 $275 $500 $875 $1,485 $2,325 $2,670 EV ($) $50 $120 $255 $420 $715 $865 $0 A) -$1,460 B) -$865 C) $865 D) $2325
Companies that compete for the same limited financial resources of the same customers are known as ____ competitors.
A. oligopolic B. total budget C. generic D. product E. brand
Rebecca works at a company where she has consistently noticed the questionable decisions and unethical behavior of her superiors. She has decided to contact the media and “blow the whistle”. Rebecca is exhibiting which kind of ethical principle?
A. Organization culture and leadership B. Decision-making processes C. Strong corporate governance D. Moral courage E. Hiring and promotion