If Activity C directly precedes both D and E on a project network, and C can be crashed three (3) times using linear programming, then:
a. crash time affects only C.
b. crash time affects only C and D.
c. crash time affects only C and E.
d. crash time affects both D and E.
D
You might also like to view...
In Milgram’s (1974) study, participants:
a. Were mostly reluctant to deliver electric shocks when the learner was a child b. Incorrectly judged the length of a line when pressured by others c. Delivered electric shocks to innocent strangers when commanded by their peers d. Were more obedient to a physically present authority figure
The total compensation an employee earns including wages, salaries, commissions, bonuses, and any compensation earned before deductions such as taxes is called ________.
Fill in the blank(s) with the appropriate word(s).
A person has acted negligently if:
a. they were incapable of reaching the victim before the harm occurred b. they tried to prevent the harm, but could not due to a lack of professional knowledge c. their conduct was not that of a reasonable person d. they admit to not liking the victim e. none of the other choices
The data a sink receives and often what data a source provides are fixed
Indicate whether the statement is true or false