You have collected the data for a time-cost CPM scheduling model analysis. The time is in days and the project "direct costs" are given here.  The indirect costs for the project are determined on a daily duration basis. If the project lasts 16 days, the total indirect costs are $400; 15 days, they will be $250; 14 days, they will be $200; and 13 days, they will be $100. If you crash this project by one day, what is the total (i.e., direct and indirect) project cost?

A. $2,150
B. $2,450
C. $2,300
D. $2,500
E. $2,400


Answer: A

Business

You might also like to view...

Because of the robustness of modern technology, businesses today see infrequent changes in their IT systems and much longer system life spans

Indicate whether the statement is true or false

Business

Marissa arrived early for her job interview. She was very excited about the opportunity to interview for a prestigious position. As she got out of the car, she got a run in her pantyhose

She was pleased to see a convenience store down the road and went there to purchase a replacement pair of pantyhose. For Marissa, the pantyhose is an example of a(n) ________. A) unsought product B) impulse product C) staple D) emergency product E) MRO product

Business

Some business customers purchase specialized services that are essential to the operation of an organization but not part of the production of a product

Indicate whether the statement is true or false

Business

The Saratoga Institute/SHRM human resources metrics are

a. a highly valued overview of many HR metrics and the formulas used to calculate them b. metrics that began to be used to measure HR effectiveness c. used to measure or audit HR programs and activities d. all of these

Business