A simple CPM network has three activities, D, E, and F. D is an immediate predecessor of E and of F. E is an immediate predecessor of F. The activity durations are D=4, E=3, F=8

A) The critical path is D-E-F, duration 15.
B) The critical path is D-F, duration 12.
C) Slack at D is 3 periods.
D) Slack at E is 3 periods.
E) Both A and C are true.


A

Business

You might also like to view...

Toro Company recognized $655,000 of cost of goods sold in 2010, in addition its implementation of a just-in-time inventory system allowed it to reduce its inventory from $325,000 at the beginning of the year to $230,000 at the end of 2010 . How much cash did Toro spend for inventory in 2010?

a. $655,000 b. $980,000 c. $560,000 d. $620,000

Business

The __________ is a measure of the degree to which family income within a country is distributed equally.

Fill in the blank(s) with the appropriate word(s).

Business

Payroll entries are made with data from the

A) wage and tax statement B) employee's earning record C) employer's quarterly federal tax return D) payroll register

Business

Under the European Union, customs duties have been eliminated among member nations

Indicate whether the statement is true or false

Business