The project represented by this network diagram has activity lengths in days and crash costs as shown in the table. The fixed cost for being on site is $450. What is the lowest total completion cost for the project?
Activity Normal Duration Crash Duration Crash Cost/Day
A 1 1
B 9 7 $475
C 4 3 $350
D 8 6 $500
E 10 8 $425
F 4 3 $300
A) $10,600
B) $11,000
C) $11,400
D) $12,000
Answer: A
You might also like to view...
________ is the communication function that seeks to build good relationships with an organization's publics
A) Advertising B) Mass marketing C) Public relations D) Promotions E) Customer service
When using modified accrual accounting, revenues should be recognized when measurable and available to finance expenditures of the current period.
Answer the following statement true (T) or false (F)
What are the two major components of media objectives?
What will be an ideal response?
Which of the following statements is true about foreign bonds??
A. The interest rate on foreign bonds is annually adjusted for inflation.? B. ?Foreign bonds are bonds sold in a foreign country and are denominated in the currency of the country in which the issue is sold. C. ?Foreign bonds are bonds sold by a foreign borrower but convertible to bonds issued in the foreign country. D. ?The term Eurobond specifically applies to any foreign bonds denominated in U.S. dollars. E. ?The interest rate on foreign bonds is adjusted annually for exchange rate fluctuations.