A project has three paths. A-B-C has a length of 25 days. A-D-C has a length of 15 days. Finally, A-E-C has a length of 20 days. Which one of the following statements is TRUE?
A) A-D-C is the critical path.
B) A-B-C has the most slack.
C) The expected duration of this project is 25 days.
D) The expected duration of this project is 25 + 15 + 20 = 60 days.
C
You might also like to view...
The business reporting process comprises accumulating, classifying, and recording data, fueling the financial reporting, business reporting, and other reporting subsystems
Indicate whether the statement is true or false
What are the main career challenges for women? What can organizations do to make better use of women's talents?
What will be an ideal response?
Chase Company rents space to a tenant for $3100 per month. The tenant currently owes rent for November and December. The tenant has agreed to pay the November, December, and January rents in full on January 15 and has agreed not to fall behind again. The adjusting entry needed on December 31 is:
A. Debit Rent Receivable, $6200; credit Rent Earned, $6200. B. Debit Rent Receivable, $9300; credit Rent Earned, $9300. C. Debit Unearned Rent, $6200; credit Rent Earned, $6200. D. Debit Rent Receivable, $3100; credit Rent Earned, $3100. E. Debit Unearned Rent, $3100; credit Rent Earned, $3100.
Which of the following involves the use of a secondary source?
A) Talking to the entry-level employees about why the duties are not being properly executed B) Surveying other companies who outsource the kinds of duties you are looking to outsource C) Reading a journal article about the perceived versus actual cost effectiveness of outsourcing D) Discussing the situation with your boss E) Speaking to outsourcing service providers about some options