Use the information in the table and sequence the six jobs using the critical ratio algorithm
Calculate the average flow times and average lateness. All jobs arrived at time zero and are ready at time zero.
Job Production Time Due Date
A 10 20
B 15 25
C 17 22
D 20 31
E 16 20
F 20 24
Job Date Received Prod Time Due Date Critical Ratio Order Flow time Late
A 0 10 20 2 sixth 98 78
B 0 15 25 1.67 fifth 88 63
C 0 17 22 1.29 third 53 31
D 0 20 31 1.55 fourth 73 42
E 0 16 20 1.25 second 36 16
F 0 20 24 1.2 first 20 0
TOTAL 98 368 230
AVERAGE 61.33 38.33
Average Flow Time = 61.33
Average Past Due = 38.33
You might also like to view...
The marketing intelligence system gathers information generated by internal reports, which includes order billing, receivables, inventory levels, stockouts, and so on
Indicate whether the statement is true or false
When a company encases its product in a blister pack to protect the item, it is using the packaging to communicate its benefits.
Answer the following statement true (T) or false (F)
Acme Global is careful to keep salaries competitive. The human resources departments checks what other organizations are paying and also considers how long an employee has been working for the organization when determining pay levels. Acme Global always pays more than minimum wage and is careful to make sure that wages are fair. It appears Acme Global is reaching the ________ level of corporate social responsibility.
A. legal B. ethical C. benevolent D. social
Which of the following is the best way to build rapport with your audience?
A) Deliver your presentation from behind a podium. B) Use the most high-tech visual aids. C) Establish a genuine connection. D) Dress in your most professional business attire.