One hundred units of part A are to be processed on a work center. The setup time is 2 hours and the run time per piece is 10 minutes. The total standard time will be:

A) 3 hours 40 minutes.
B) 1000 minutes.
C) 2 hours 10 minutes.
D) 10 minutes.
E) 1120 minutes.


E

Trades & Technology

You might also like to view...

The engine side of the transmission input shaft is supported by a pilot bearing or sintered bronze bushing pressed into the end of the crankshaft.

Answer the following statement true (T) or false (F)

Trades & Technology

The percent price increase p on a variety of retail food prices over a 1-year period varied from 5% to 10% in all cases. Because of the distribution of p values, the assumed probability distribution for the next year is

Trades & Technology

The national debt increased most during

A. Franklin Roosevelt's New Deal. B. Herbert Hoover's administration. C. World War II. D. World War I. E. the 1920s.

Trades & Technology

When testing an ECT sensor on a vehicle, a digital multimeter can be used and the signal wire tested with the connector attached with the ignition on (engine off). What setting should the technician use to test the sensor?

A) Hz (hertz) B) Ohms C) DC volts D) AC volts

Trades & Technology