In a construction contract, there is a $1000 per day estimate of damages for each day that the contract runs over the completion date. The contractor is 30 days late when the job is completed, resulting in a prospective damage award of $30,000 . What is this type of clause, and when will it be enforced?


This type of clause is known as a liquidated damages clause. Generally this type of clause will be enforced if, at the time of creating the contract, it was very difficult to estimate actual damages, and the liquidated amount is reasonable. In this case, if the total construction contract involved millions of dollars, the estimate of damages may reasonably amount to a $1000 per day. If the construction project is a small one, the court may see this amount as too much and not enforce the clause.

Business

You might also like to view...

Use eye-catching graphics in an illustration:

a. to set a serious tone b. to focus attention on the data c. both of the above d. none of the above

Business

Sustainability practices focus on ______.

a. reducing resource usage b. reducing waste c. more efficient use of existing capacity d. producing more to make use of existing capacity

Business

Write a short note on race-norming.

What will be an ideal response?

Business

Commercial off-the-shelf software requires permission from the software developers before it can be installed and used

Indicate whether the statement is true or false

Business