What is the explosion of the MPS and what are the outputs?
What will be an ideal response?
MRP translates, or explodes, the MPS and other sources of demand into the requirements needed for all of the subassemblies, components, and raw materials the firm needs to produce parent items. This process generates the material requirements plan for each component item. An item's gross requirements are derived from three sources: 1. The MPS for immediate parents that are end items; 2. The planned order releases (not the gross requirements, scheduled receipts, or planned receipts) for immediate parents below the MPS level; 3. Any other requirements not originating in the MPS, such as the demand for replacement parts.
You might also like to view...
The liability of corporate stockholders is limited to their percentage share of ownership
Indicate whether the statement is true or false
Marketing stimuli include which of the following?
A) economic stimuli B) price stimuli C) technological stimuli D) social stimuli E) cultural stimuli
A break-even chart shows the total cost and total revenue expected at various sales volume levels
Indicate whether the statement is true or false
All of the following is true with regard to cultural issues when locating in foreign countries except ______.
a. it is critical to understand the religious and cultural practices in overseas locations b. companies have to deal with gender differences in labor practices and in promoting products that can be sold to consumers c. a firm’s managers need to be fluent in the foreign country’s language d. it is critical to assume that every product will appeal to consumers in other cultures