Match the following terms to their meanings:

I. 24 Hours calendar
II. Night Shift calendar
III. Standard calendar
IV. Manually Scheduled
V. Auto Scheduled

A. Based on a shift schedule of Monday night through Saturday morning
B. Based on a 40-hour work week with an 8-hour work day
C. Assigns a schedule with continuous work
D. Uses Project's 2013 scheduling engine
E. Task dates are not calculated or adjusted by Project's 2013 scheduling engine


C, A, B, E, D

Computer Science & Information Technology

You might also like to view...

Perform the following task for an array called fraction:

Declare constant ArraySize initialized to 10.

Computer Science & Information Technology

A 32-bit driver can be used in a 64-bit operating system.

Answer the following statement true (T) or false (F)

Computer Science & Information Technology

What is not true about a split form?

A. You can pick one record for the top and a different record for the bottom B. Combines two views of the same record C. Top section uses a stacked layout D. Bottom section uses a tabular layout

Computer Science & Information Technology

MC An object is .

a) a programming encapsulation that mimics real life objects b) a group of programmed code that is not necessarily related c) the hardware and software of the computer d) a set code that is difficult to update, but never needs changing

Computer Science & Information Technology