The forward pass in a critical path algorithm involves:
A. Calculating the late finish and late start for each task.
B. Calculating the late finish and the earliest possible start times for each task.
C. Calculating the earliest possible start and finish times for each task.
D. Calculating the earliest possible start and late start for each task.
C. Calculating the earliest possible start and finish times for each task.
Explanation:
The forward pass calculates the earliest start and finish dates.
You might also like to view...
Describe persuasive communication within an organization
According to the Anglo culture cluster, the least desirable leader behavior is ______.
A. charismatic/value-based leadership B. participative leadership C. humane-oriented leadership D. self-protective leadership
Bonds that mature at different intervals from the date of issue are ____________________ bonds.
Fill in the blank(s) with the appropriate word(s).
Louisa and her neighbour Eva had boundary disputes for many years. Their last argument ended with Eva promising to "get Louisa "any way I can
" One night Eva hears a noise and looks out to see someone who based on her physical appearance she thinks is Louisa destroying her plants. Eva called the police and reported the incident. After an investigation Louisa was arrested and spent a night in jail. Louisa is found not guilty at trial due to a lack of evidence. It was later discovered Eva had been mistaken when identifying Louisa as the one who destroyed her plants. Which of the following statements best describes the legal position? A) Louisa can successfully sue Eva for the tort of malicious prosecution. B) Louisa can successfully sue Eva for intrusion upon seclusion C) Eva is liable for the tort of false imprisonment D) Eva is liable for the tort of nuisance E) Eva is not liable for anything