In one week a work center produces 130 standard hours of work. The hours scheduled are 120, and

105 hours are actually worked. The utilization is:

A) 87.5%. B) 108.3%. C) 92.3%. D) 123.8%. E) 80.8%.


A

Business

You might also like to view...

Identify the four pillars of brand equity, according to BrandAsset® Valuator model

A) relevance, performance, bonding, and advantage B) presence, performance, advantage, and bonding C) energized differentiation, relevance, esteem, and knowledge D) brand salience, brand feelings, brand imagery, and brand performance E) energized differentiation, esteem, brand feelings, and brand salience

Business

Which statement best describes the concept of equivalent units of production?

A) Equivalent units are the measure of a period's output B) Equivalent units are the units completed in a department C) Equivalent units are the total of the units produced by all departments D) Equivalent units are the number of units completed at the end of the last process

Business

Sales promotion objectives should be consistent with the organization's overall objectives and its marketing objectives.

Answer the following statement true (T) or false (F)

Business

What is a carry trade?

What will be an ideal response?

Business