Which activity should be crashed to reduce the project completion by 2 days?
A) Crash activity B by 1 day and Activity C by 1 day.
B) Crash activity E by 2 days.
C) Crash activity C by 1 day and activity E by 1 day.
D) Crash activity B by 2 days.
Answer: C
You might also like to view...
Which statement is true about a product market?
A. The cost of labor does not affect the product market because it is an insignificant part of an organization's costs. B. Organizations in a product market must increase the cost of labor every quarter. C. Product-market considerations are of particular concern to a company when its customers place greater importance on product rather than price. D. Product markets typically place a lower limit on the pay an organization will offer its employees. E. Organizations in a product market are competing to serve the same customers.
Knollwood Corporation issued $281,000 of 30-year, 8 percent bonds at 106 on one of its semi-annual interest dates. The straight-line method of amortization is to be used. After 11 years, what is the carrying value of the bonds?
a. $289,430 b. $289,992 c. $288,025 d. $291,678
The ultimate goal of biomimicry is to eliminate waste altogether rather than reducing it.
Answer the following statement true (T) or false (F)
Identify two aspects of advertising that a marketer can control and two aspects of advertising that a marketer cannot control
What will be an ideal response?