Describe how time—cost tradeoffs for project activities should be identified and analyzed
What will be an ideal response?
There are always time—cost tradeoffs in project management situations. Overall project length is driven by the length of the critical path, so if it is necessary to finish the project more quickly, the activities that should be shortened are those on the critical path. Whether the goal is to reduce the project's length to avoid a penalty, meet a deadline, or to reach an incentive, the cheapest activities on the critical path should be attacked first. If the objective is to minimize costs, then the project manager should reduce the critical path by expediting activities until the increase in direct costs exceeds the savings that can be gained. If the objective is to finish the project in a certain number of days, the project manager must continue to reduce activity lengths until that target is reached regardless of expense.
You might also like to view...
The amount of money spent on the whole category of a product is known as:
A) share of category requirements. B) size of wallet. C) share of wallet. D) customer lifetime value.
Experienced quality of service is determined by:
A) an image the customer forms after the service encounter. B) market communications and image of the company. C) past experiences that the customer had with company. D) word of mouth communication and customer needs.
When a major corporation develops its own trademark and over time it becomes very valuable, the trademark may not be shown on their balance sheet due lack of a material cost
Indicate whether the statement is true or false
What are two of the five behaviors, given in the textbook, which an empowering leader would use? Explain in detail.
What will be an ideal response?