Contract requirements state that a project must be completed within 180 working days, or it will incur penalties for late completion

Analysis of the activity network reveals an estimated project time of 145 working days with a project variance of 400. What is the probability that the project will be completed before the late-payment deadline?
A) 0.0401
B) 0.4599
C) 0.8056
D) 0.9599
E) near 1.0000, or almost certain


D

Business

You might also like to view...

As described in the text, Valeant Pharmaceuticals made a legal move to buy a wide range of heart medications and raise prices on all of them. How did this primarily damage the company?

a. It damaged its reputation and resulted in a fall in share price. b. Government prosecution for monopolistic practices followed. c. It emboldened competitors to make similar moves. d. It drove its customer base into poorer health.

Business

Once the adjusting entries are posted, the Adjusted Trial Balance is prepared to

A) verify that the debits and credits are in balance. B) verify that all of the adjustments were posted in the correct accounts. C) verify that the net income (loss) is correct for the period. D) verify the correct flow of accounts into the financial statements.

Business

Because systematic risk measures how much an asset's return co-moves with the market, it ________

A) can be diversified away with the appropriate hedging B) cannot be diversified away C) is partially driven by idiosyncratic risk D) can be completely eliminated using international securities

Business

________ software provides capabilities that are common across all organizations and industries

A) Vertical-market application B) Custom-developed C) Horizontal-market application D) Off-the-shelf with alterations

Business