Fairview Industries is preparing its aggregate plan for the second half of the year. The table below contains monthly demand estimates and working days per month

Complete the table by computing total demand, demand per day (for each month), and the average requirement (in units per day) over the six-month planning horizon. Prepare a graph of forecast demand and level production, by months, for the planning period. Label your graph carefully.

Month Expected Demand Production Days Demand per Day
July 18,000 20
August 21,000 23
September 17,500 21
October 12,500 21
November 12,000 20
December 13,500 21
TOTAL


Month Expected Demand Production Days Demand per Day
July 18,000 20 900.00
August 21,000 23 913.04
September 17,500 21 833.33
October 12,500 21 595.24
November 12,000 20 600.00
December 13,500 21 642.86
TOTAL 94,500 126 Average =750

Business

You might also like to view...

To pierce the corporate veil means to shield the shareholders from personal liability

Indicate whether the statement is true or false

Business

An objective of the EU is to promote economic and social progress among member states

Indicate whether the statement is true or false

Business

Which of the following is acquired (in addition to a cash payoff) when the holder of a call futures exercises?

A. A long position in a futures contract B. A short position in a futures contract C. A long position in the underlying asset D. A short position in the underlying asset

Business

The portfolio standard deviation will always be less than the standard deviation of any asset in the portfolio

Indicate whether this statement is true or false.

Business