In most construction schedules, activity duration should be no shorter than ____.

A. one hour
B. one day
C. three hours
D. three days


Answer: B

Trades & Technology

You might also like to view...

The service consultant is asked by a customer to install a used part that is not designed for the vehicle being repaired. The best response from the service consultant is_________

A. Approve the request and do the repair B. Reject the request because it will put the company at risk if it fails C. Reject the request because it will not help the customer D. Reject the request because it will not promote part sales

Trades & Technology

List three ways food can become contaminated

What will be an ideal response?

Trades & Technology

A two-input NAND gate has inputs of 1 and 0; the output is 0

Indicate whether the statement is true or false

Trades & Technology

Show by direct analytical integration that the integral of the function, g (t) = A sin (2?t) B sin (4?t) is zero over the interval, ?1/2 < t < 1/2.

What will be an ideal response?

Trades & Technology