If, for some reason, the project must be expedited to meet an earlier date, which of the following actions would the project manager take first?
A. Check to see which activities cost the least
B. Check to see which activities are on the critical path
C. Check to see which activities have the longest duration
D. Check to see which activities have the highest risk
E. Check to see which activities have the most slack
Answer: B
You might also like to view...
Companies prefer buyers who are both attitudinally and behaviorally loyal.
Answer the following statement true (T) or false (F)
Which of the following is not true about auditing stockholders' equity transactions?
a. The auditor usually uses a substantive approach. b. The number of equity transactions with outside parties is usually small. c. The dollar amount is usually immaterial. d. An approach using only tests of details is most commonly used to audit equity accounts.
Another term for e-mail etiquette is ______.
A. rules of order B. grapevine C. netiquette D. spam protocol
User-driven innovation is often resisted by companies for many reasons. Which one of the following is NOT one of those reasons?
a. Companies believe customers lack the skill base that the product requires. b. Companies believe customers lack sophisticated knowledge. c. Companies believe it gives customers too much power. d. Engineers view customer innovators as rivals who undermine or challenge their creativity. e. Customers come up with great ideas that the company may not have thought of.