If a project is expected to be completed in 68 days with a project variance of 21 days, what is the probability that the project will be completed within 70 days?
a. between 35% and 40%
b. between 45% and 50%
c. between 55% and 60%
d. between 65% and 70%
d. between 65% and 70%
You might also like to view...
Which of the following models can be used when demand exhibits both trend and seasonal patterns?
a. simple exponential smoothing b. second-order or double smoothing c. third-order or triple smoothing d. complex exponential smoothing
Patagonia shows that a company that transforms its corporate strategy to emphasize "doing good" socially and environmentally cannot do well economically.
Answer the following statement true (T) or false (F)
Saturn Corporation issued $300,000 par value 10-year bonds at 107 on January 1, 20X3, which Star Corporation purchased. On July 1, 20X7, Pluto Corporation purchased $120,000 face value of Saturn bonds from Star. The bonds pay 12 percent interest annually on December 31. The preparation of consolidated financial statements for Saturn and Pluto at December 31, 20X9, required the following consolidation entry: Bonds Payable 120,000 Premium on Bonds Payable 2,520 Interest Income 14,760 Investment in Saturn Corporation Bonds 118,920 Interest Expense 13,560 Investment in Saturn Corporation Stock 3,120 NCI in NA of Saturn Corp. 1,680 Based on the information given above, if 20X9 consolidated net income of $50,000 would have been reported
without the consolidation entry provided, what amount will actually be reported? A. $48,200 B. $49,400 C. $48,800 D. $47,900
_______ is the level of measurement where outcomes can be rank ordered.
a.Nominal b.Ordinal c.Ratio d.Interval